Cause & Consequence
- Other
Incident Location
Drilling unit
Incident Activity
Well services / intervention
Incident Info Source
Centrica Energy (formally Venture Production plc)&
Specific Incident Equipment
Slickline Dual BOP Slickline Stuffing Box
Lessons Identified
No details available.
Incident Recommendations
Equipment
Ensure the slickline stuffing box is checked after redress by the 2nd slickline operator to verify correct make up.
Ensure that each ram on the BOP is function tested on the well with all hoses connected and witnessed.
A design review of the stuffing box assembly and make up procedure.
Development and implementation of a hose management system for hoses that provide hydraulic fluid to safety critical equipment.
Review BOP hydraulic control system. The BOP should have a separate hydraulic supply to open and close each ram.
Observations
Re-position the slickline BOP control panel to a position that can be more easily accessed, without the need to cross below the slickline.